025-599-105 - BRIDGE 25616 & APPROACH GRADINGICON Constructors, LLC Prahm Construction Inc. Minnowa Construction Inc Duininck, Inc. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$20,800.00$20,800.00$32,000.00$32,000.00$40,000.00$40,000.00$82,125.00$82,125.00
2101.511CLEARING & GRUBBINGLS1$3,500.00$3,500.00$2,500.00$2,500.00$5,000.00$5,000.00$5,000.00$5,000.00
2105.515UNCLASSIFIED EXCAVATIONCU YD1,248$4.75$5,928.00$5.50$6,864.00$12.00$14,976.00$12.75$15,912.00
2105.522SELECT GRANULAR BORROW (CV) (P)C Y653$18.50$12,080.50$22.00$14,366.00$30.00$19,590.00$18.00$11,754.00
2118.607AGGREGATE SURFACING (CV) CLASS 5 (P)C Y286$21.50$6,149.00$30.00$8,580.00$35.00$10,010.00$30.00$8,580.00
2123.5072.5 CU YD SHOVELHOUR20$125.00$2,500.00$120.00$2,400.00$150.00$3,000.00$170.00$3,400.00
2123.509DOZERHOUR20$125.00$2,500.00$120.00$2,400.00$125.00$2,500.00$170.00$3,400.00
2401.501STRUCTURAL CONCRETE (3Y43) (P)C Y84$550.00$46,200.00$550.00$46,200.00$500.00$42,000.00$750.00$63,000.00
2401.512BRIDGE SLAB CONCRETE (3Y33A) (P)S F2,968$32.00$94,976.00$30.00$89,040.00$34.00$100,912.00$45.00$133,560.00
2401.513TYPE F (TL-4) RAILING CONCRETE (3Y46A) (P)L F198$85.00$16,830.00$80.00$15,840.00$75.00$14,850.00$130.00$25,740.00
2401.541REINFORCEMENT BARS (EPOXY COATED) (P)LB47,040$1.00$47,040.00$1.00$47,040.00$1.00$47,040.00$1.15$54,096.00
2401.601SLOPE PREPARATIONLS1$4,500.00$4,500.00$2,500.00$2,500.00$15,000.00$15,000.00$2,500.00$2,500.00
2401.601STRUCTURE EXCAVATIONLS1$2,500.00$2,500.00$5,000.00$5,000.00$35,000.00$35,000.00$15,000.00$15,000.00
2402.521STRUCTURAL STEEL (3306) (P)LB510$5.00$2,550.00$4.00$2,040.00$8.00$4,080.00$4.00$2,040.00
2402.546FLOOR DRAIN TYPE B702EACH3$250.00$750.00$200.00$600.00$500.00$1,500.00$175.00$525.00
2442.501REMOVE EXISTING BRIDGELS1$30,000.00$30,000.00$22,000.00$22,000.00$40,000.00$40,000.00$55,000.00$55,000.00
2452.510STEEL H-PILING DRIVEN 10"L F240$1.00$240.00$1.00$240.00$5.00$1,200.00$1.00$240.00
2452.510STEEL H-PILING DRIVEN 12"L F240$1.00$240.00$1.00$240.00$5.00$1,200.00$1.00$240.00
2452.511STEEL H-PILING DELIVERED 10"L F240$32.00$7,680.00$26.00$6,240.00$40.00$9,600.00$23.00$5,520.00
2452.511STEEL H-PILING DELIVERED 12"L F240$37.00$8,880.00$31.00$7,440.00$50.00$12,000.00$29.00$6,960.00
2452.520STEEL H-TEST PILE 40 FT LONG 10"EACH2$6,000.00$12,000.00$9,000.00$18,000.00$5,000.00$10,000.00$4,400.00$8,800.00
2452.520STEEL H-TEST PILE 40 FT LONG 12"EACH2$7,000.00$14,000.00$10,000.00$20,000.00$6,000.00$12,000.00$4,750.00$9,500.00
2452.602PILE TIP PROTECTION 10"EACH10$100.00$1,000.00$100.00$1,000.00$125.00$1,250.00$105.00$1,050.00
2452.602PILE TIP PROTECTION 12"EACH10$150.00$1,500.00$120.00$1,200.00$150.00$1,500.00$125.00$1,250.00
2452.60320" STEEL PILE SHELLSL F150$100.00$15,000.00$140.00$21,000.00$85.16$12,774.00$70.00$10,500.00
2501.51115" CS PIPE CULVERTL F30$25.00$750.00$30.00$900.00$45.00$1,350.00$32.00$960.00
2501.51515" GS PIPE APRONEACH2$125.00$250.00$300.00$600.00$1,000.00$2,000.00$200.00$400.00
2502.502DRAINAGE SYSTEM TYPE (B910)LS1$1,500.00$1,500.00$1,000.00$1,000.00$5,000.00$5,000.00$1,100.00$1,100.00
2511.501RANDOM RIPRAP CLASS IIIC Y300$36.00$10,800.00$50.00$15,000.00$35.00$10,500.00$40.00$12,000.00
2563.601TRAFFIC CONTROLLS1$1,450.00$1,450.00$3,500.00$3,500.00$2,000.00$2,000.00$2,400.00$2,400.00
2573.502SILT FENCE, TYPE MSL F1,246$1.60$1,993.60$3.00$3,738.00$1.75$2,180.50$1.70$2,118.20
2573.505FLOTATION SILT CURTAIN TYPE WORK AREALIN FT200$15.00$3,000.00$20.00$4,000.00$15.00$3,000.00$16.75$3,350.00
2573.512TEMPORARY DITCH CHECK TYPE 3LIN FT56$3.00$168.00$2.00$112.00$3.50$196.00$4.25$238.00
2573.602TEMPORARY SEDIMENT TRAPEACH1$300.00$300.00$400.00$400.00$500.00$500.00$150.00$150.00
2575.572RAPID STABILIZATION METHOD 4S Y29$10.00$290.00$52.00$1,508.00$10.00$290.00$8.25$239.25
 Totals for project 025-599-105 $379,845.10 $405,488.00 $483,998.50 $548,647.45
 
Contract Total:$379,845.10$405,488.00$483,998.50$548,647.45