025-599-113 - BRIDGE 25J82Schumacher Excavating Inc Swenke Co. Inc. Fitzgerald Excavating and Trucking Inc. Landwehr Construction Inc Midwest Contracting, LLC 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$3,500.00$3,500.00$9,000.00$9,000.00$4,000.00$4,000.00$6,900.00$6,900.00$14,000.00$14,000.00
2101.511CLEARING & GRUBBINGLS1$3,000.00$3,000.00$5,000.00$5,000.00$5,000.00$5,000.00$6,164.00$6,164.00$2,000.00$2,000.00
2105.522SELECT GRANULAR BORROW (CV) (P)C Y451$16.50$7,441.50$20.00$9,020.00$14.00$6,314.00$26.50$11,951.50$25.00$11,275.00
2105.523COMMON BORROW (LV)C Y961$11.00$10,571.00$8.00$7,688.00$11.00$10,571.00$11.50$11,051.50$6.00$5,766.00
2105.601TEMPORARY STREAM DIVERSION SYSTEMLS1$3,000.00$3,000.00$3,000.00$3,000.00$2,000.00$2,000.00$4,760.00$4,760.00$1,500.00$1,500.00
2105.607UNCLASSIFIED EXCAVATION (P)C Y1,282$7.00$8,974.00$3.00$3,846.00$5.50$7,051.00$5.00$6,410.00$4.00$5,128.00
2118.607AGGREGATE SURFACING (CV) CLASS 5 (P)C Y190$23.10$4,389.00$23.00$4,370.00$20.00$3,800.00$30.00$5,700.00$27.00$5,130.00
2123.5072.5 CU YD SHOVELHOUR10$160.00$1,600.00$1.00$10.00$100.00$1,000.00$194.00$1,940.00$100.00$1,000.00
2412.51114X11 PRECAST CONCRETE BOX CULVERT CL 2L F48$892.00$42,816.00$900.00$43,200.00$1,275.00$61,200.00$1,160.00$55,680.00$1,400.00$67,200.00
2412.51214X11 PRECAST CONCRETE BOX CULV END SECT TYPE 1EACH2$17,400.00$34,800.00$16,000.00$32,000.00$19,000.00$38,000.00$18,370.00$36,740.00$24,000.00$48,000.00
2442.501REMOVE EXISTING BRIDGELS1$5,000.00$5,000.00$6,000.00$6,000.00$10,000.00$10,000.00$7,500.00$7,500.00$5,000.00$5,000.00
2451.503GRANULAR BACKFILL (CV) (P)C Y158$19.60$3,096.80$30.00$4,740.00$14.00$2,212.00$24.00$3,792.00$22.00$3,476.00
2451.509AGGREGATE BEDDING (CV) (P)C Y159$25.60$4,070.40$40.00$6,360.00$19.00$3,021.00$25.00$3,975.00$35.00$5,565.00
2511.501RANDOM RIPRAP CLASS IVC Y168$51.00$8,568.00$55.00$9,240.00$30.00$5,040.00$60.00$10,080.00$45.00$7,560.00
2563.601TRAFFIC CONTROLLS1$600.00$600.00$1,000.00$1,000.00$2,000.00$2,000.00$1,500.00$1,500.00$1,000.00$1,000.00
2573.502SILT FENCE, TYPE MSL F537$2.50$1,342.50$2.00$1,074.00$2.00$1,074.00$3.80$2,040.60$2.00$1,074.00
2575.602RAPID STABILIZATION (METHOD 1)BALE12$7.00$84.00$50.00$600.00$5.00$60.00$81.00$972.00$35.00$420.00
 Totals for project 025-599-113 $142,853.20 $146,148.00 $162,343.00 $177,156.60 $185,094.00
 
025-599-114 - BRIDGE 25J83Schumacher Excavating Inc Swenke Co. Inc. Fitzgerald Excavating and Trucking Inc. Landwehr Construction Inc Midwest Contracting, LLC 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$3,500.00$3,500.00$12,000.00$12,000.00$15,000.00$15,000.00$4,200.00$4,200.00$15,000.00$15,000.00
2101.511CLEARING & GRUBBINGLS1$3,000.00$3,000.00$5,000.00$5,000.00$5,000.00$5,000.00$7,500.00$7,500.00$3,500.00$3,500.00
2104.521SALVAGE FENCEL F347$1.50$520.50$4.00$1,388.00$3.00$1,041.00$3.20$1,110.40$3.00$1,041.00
2105.522SELECT GRANULAR BORROW MOD (CV) (P)C Y548$12.40$6,795.20$25.00$13,700.00$14.00$7,672.00$20.50$11,234.00$20.00$10,960.00
2105.523COMMON BORROW (EV)C Y2,793$8.50$23,740.50$8.00$22,344.00$11.00$30,723.00$10.00$27,930.00$8.00$22,344.00
2105.601TEMPORARY STREAM DIVERSION SYSTEMLS1$2,000.00$2,000.00$5,000.00$5,000.00$2,000.00$2,000.00$5,700.00$5,700.00$1,500.00$1,500.00
2105.607UNCLASSIFIED EXCAVATIONC Y1,172$7.00$8,204.00$3.00$3,516.00$5.50$6,446.00$4.30$5,039.60$4.00$4,688.00
2118.607AGGREGATE SURFACING (CV) CLASS 5 (P)C Y223$21.50$4,794.50$23.00$5,129.00$20.00$4,460.00$23.00$5,129.00$24.00$5,352.00
2123.5072.5 CU YD SHOVELHOUR20$160.00$3,200.00$1.00$20.00$100.00$2,000.00$194.00$3,880.00$100.00$2,000.00
2123.509DOZERHOUR20$160.00$3,200.00$1.00$20.00$100.00$2,000.00$198.00$3,960.00$100.00$2,000.00
2412.51114X10 PRECAST CONCRETE BOX CULVERT CLASS 3L F74$940.00$69,560.00$1,000.00$74,000.00$1,375.00$101,750.00$1,225.00$90,650.00$1,400.00$103,600.00
2412.51214X10 PRECAST CONCRETE BOX CULV END SECTEACH2$16,343.00$32,686.00$15,000.00$30,000.00$18,000.00$36,000.00$16,965.00$33,930.00$23,000.00$46,000.00
2442.501REMOVE EXISTING BRIDGELS1$5,000.00$5,000.00$6,000.00$6,000.00$10,000.00$10,000.00$7,700.00$7,700.00$4,000.00$4,000.00
2451.503GRANULAR BACKFILL (CV) (P)C Y255$16.00$4,080.00$35.00$8,925.00$14.00$3,570.00$20.30$5,176.50$20.00$5,100.00
2451.503GRANULAR BACKFILL (CV) (P)C Y249$16.00$3,984.00$35.00$8,715.00$14.00$3,486.00$20.40$5,079.60$20.00$4,980.00
2451.509AGGREGATE BEDDING (CV) (P)C Y189$24.00$4,536.00$40.00$7,560.00$20.00$3,780.00$24.00$4,536.00$35.00$6,615.00
2511.501RANDOM RIPRAP CLASS IVC Y308$40.00$12,320.00$55.00$16,940.00$30.00$9,240.00$53.00$16,324.00$45.00$13,860.00
2557.603INSTALL SALVAGED FENCEL F347$3.00$1,041.00$6.00$2,082.00$3.00$1,041.00$5.70$1,977.90$4.00$1,388.00
2563.601TRAFFIC CONTROLLS1$500.00$500.00$1,000.00$1,000.00$2,000.00$2,000.00$1,760.00$1,760.00$1,000.00$1,000.00
2573.502SILT FENCE, TYPE MSL F1,021$2.25$2,297.25$2.00$2,042.00$2.00$2,042.00$3.50$3,573.50$2.00$2,042.00
2573.602TEMPORARY SEDIMENT TRAPEACH1$100.00$100.00$1.00$1.00$800.00$800.00$1,250.00$1,250.00$350.00$350.00
2575.602RAPID STABILIZATION (METHOD 1)BALE35$7.00$245.00$50.00$1,750.00$5.00$175.00$55.00$1,925.00$25.00$875.00
 Totals for project 025-599-114 $195,303.95 $227,132.00 $250,226.00 $249,565.50 $258,195.00
 
025-599-115 - BRIDGE 25J84Schumacher Excavating Inc Swenke Co. Inc. Fitzgerald Excavating and Trucking Inc. Landwehr Construction Inc Midwest Contracting, LLC 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$3,500.00$3,500.00$12,000.00$12,000.00$25,000.00$25,000.00$3,900.00$3,900.00$15,000.00$15,000.00
2101.511CLEARING & GRUBBINGLS1$3,000.00$3,000.00$5,000.00$5,000.00$5,000.00$5,000.00$9,700.00$9,700.00$4,000.00$4,000.00
2104.501REMOVE PIPE CULVERTSL F33$2.00$66.00$10.00$330.00$5.00$165.00$15.60$514.80$4.00$132.00
2105.522SELECT GRANULAR BORROW (CV) (P)C Y957$12.00$11,484.00$25.00$23,925.00$14.00$13,398.00$22.00$21,054.00$20.00$19,140.00
2105.523COMMON BORROW (LV)C Y4,033$7.50$30,247.50$8.00$32,264.00$11.00$44,363.00$8.60$34,683.80$8.00$32,264.00
2105.601TEMPORARY STREAM DIVERSION SYSTEMLS1$5,000.00$5,000.00$5,000.00$5,000.00$2,000.00$2,000.00$5,800.00$5,800.00$1,500.00$1,500.00
2105.607UNCLASSIFIED EXCAVATIONC Y1,900$7.00$13,300.00$3.00$5,700.00$5.50$10,450.00$4.30$8,170.00$4.00$7,600.00
2118.607AGGREGATE SURFACING (CV) CLASS 5 (P)C Y445$20.00$8,900.00$23.00$10,235.00$20.00$8,900.00$24.40$10,858.00$24.00$10,680.00
2123.5072.5 CY SHOVELHOUR20$160.00$3,200.00$1.00$20.00$100.00$2,000.00$194.00$3,880.00$100.00$2,000.00
2123.509DOZERHOUR20$160.00$3,200.00$1.00$20.00$100.00$2,000.00$198.00$3,960.00$100.00$2,000.00
2412.51116X11 PRECAST CONCRETE BOX CULVERT CLASS 3L F50$1,126.00$56,300.00$1,250.00$62,500.00$1,620.00$81,000.00$1,535.00$76,750.00$1,700.00$85,000.00
2412.51216X11 PRECAST CONCRETE BOX CULV END SECEACH2$19,640.00$39,280.00$17,000.00$34,000.00$21,000.00$42,000.00$21,470.00$42,940.00$24,000.00$48,000.00
2442.501REMOVE EXISTING BRIDGELS1$7,000.00$7,000.00$6,000.00$6,000.00$10,000.00$10,000.00$13,000.00$13,000.00$4,500.00$4,500.00
2451.503GRANULAR BACKFILL (CV) (P)C Y82$15.00$1,230.00$35.00$2,870.00$14.00$1,148.00$23.00$1,886.00$20.00$1,640.00
2451.503GRANULAR BACKFILL (CV) (P)C Y241$15.00$3,615.00$35.00$8,435.00$14.00$3,374.00$22.00$5,302.00$20.00$4,820.00
2451.509AGGREGATE BEDDING (CV) (P)C Y161$23.00$3,703.00$40.00$6,440.00$20.00$3,220.00$24.00$3,864.00$35.00$5,635.00
2501.51112" CS PIPE CULVERTL F40$21.00$840.00$40.00$1,600.00$25.00$1,000.00$38.50$1,540.00$30.00$1,200.00
2501.51512" CS PIPE APRONEACH2$110.00$220.00$800.00$1,600.00$200.00$400.00$354.00$708.00$200.00$400.00
2511.501RANDOM RIPRAP CLASS IVC Y367$38.00$13,946.00$55.00$20,185.00$30.00$11,010.00$55.00$20,185.00$45.00$16,515.00
2563.601TRAFFIC CONTROLLS1$500.00$500.00$1,000.00$1,000.00$2,000.00$2,000.00$1,750.00$1,750.00$1,000.00$1,000.00
2573.502SILT FENCE, TYPE MSL F1,351$2.25$3,039.75$2.00$2,702.00$2.00$2,702.00$3.50$4,728.50$2.00$2,702.00
2573.602TEMPORARY SEDIMENT TRAPEACH1$100.00$100.00$1.00$1.00$800.00$800.00$1,800.00$1,800.00$350.00$350.00
2575.523EROSION CONTROL BLANKETS CATEGORY 4S Y750$2.13$1,597.50$3.00$2,250.00$2.00$1,500.00$4.40$3,300.00$3.00$2,250.00
2575.602RAPID STABILIZATION (METHOD 1)BALE53$7.00$371.00$50.00$2,650.00$5.00$265.00$51.00$2,703.00$25.00$1,325.00
 Totals for project 025-599-115 $213,639.75 $246,727.00 $273,695.00 $282,977.10 $269,653.00
 
Contract Total:$551,796.90$620,007.00$686,264.00$709,699.20$712,942.00